Date of publication | Details | Reference materials |
11 May 2022 | CHESS Replacement project update – confirmation of delay to April 2023 go-live | Stakeholder communication |
29 April 2022 | April 2022 – Documentation Release Notes | |
27 April 2022 | April 2022 - ITE2 Drop Notes | |
20 April 2022 | Implementation & Transition Working Group Q&A – 7 April 2022 | I&T – 7 April 2022 |
4 April 2022 | PISP Readiness Working Group Q&A - 23 March 2022 | Q&A – 23 March 2022 |
31 March 2022 | March 2022 – Documentation Release Notes | Release Notes |
31 March 2022 | Clearing & Settlement Readiness Working Group Q&A - 16 March 2022 | Q&A – 16 March 2022 |
28 March 2022 | CHESS Replacement project update – changes to software release timing and implications for project milestones | Stakeholder communication |
22 March 2022 | EY - Independent assessment of ASX’s Assurance Program for its Implementation of the CHESS Replacement Program | Independent Expert Report |
7 March 2022 | Implementation & Transition Working Group Q&A – 23 February 2022 | |
4 March 2022 | Clearing & Settlement Readiness Working Group Q&A - 16 February 2022 | CSPR WG - 16 Feb 2022 |
28 February 2022 | February 2022 – Documentation Release Notes | |
23 February 2022 | Software Provider Readiness Working Group Q&A – 9 February 2022 | |
31 January 2022 | Industry Test Environment - code drop (v1.2) | Release Notes |
31 January 2022 | January 2022 – Documentation Release Notes | Release Notes |
31 January 2022 | Software Provider Readiness Working Group Q&A – 19 January 2022 | Q&A – 19 January 2022 |
21 December 2021 | ASX CHESS Replacement Project Newsletter - December 2021 | |
21 December 2021 | Implementation & Transition Working Group Q&A – 27 October 2021 | Q&A – 15 December 2021 |
21 December 2021 | Software Provider Readiness Working Group Q&A - 17 November 2021 | Q&A – 8 December 2021 |
17 December 2021 | Cutover and Migration Strategy | |
17 December 2021 | December 2021 - Documentation Release Notes | |
30 November 2021 | ASX CHESS Replacement – Industry Test Environment (ITE1) is now open | Media Release |
30 November 2021 | ASX CHESS Replacement – Industry Test Environment (ITE1) is now open | Stakeholder communication |
30 November 2021 | November 2021 - ITE1 Release Notes | Release notes |
30 November 2021 | ASX CHESS Replacement Documentation Release - November 2021 Release notes | Release notes |
25 November 2021 | Software Provider Readiness Working Group Q&A - 17 November 2021 | Q&A - 17 November 2021 |
2 November 2021 | Implementation & Transition Working Group Q&A – 27 October 2021 | Q&A - 13 October 2021 |
29 October 2021 | ASX CHESS Replacement Documentation Release - October 2021 Release notes | Release notes |
26 October 2021 | Software Provider Readiness Working Group Q&A - 13 October 2021 | Q&A - 13 October 2021 |
15 October 2021 | ASX CHESS Replacement Project Newsletter - October 2021 | Newsletter - October 2021 |
11 October 2021 | Implementation & Transition Working Group Q&A – 29 September 2021 | |
30 September 2021 | ASX CHESS Replacement Documentation Release - September 2021 Release notes | |
29 September 2021 | ASX CHESS Replacement System Access Pricing | Information sheet |
27 September 2021 | Technical Documentation - CDE 10 code drop | Release notes |
23 September 2021 | Software Provider Readiness Working Group Q&A – 15 September 2021 |
Q&A – 15 September 2021 |
2 September 2021 | ASX CHESS Replacement Project Newsletter - September 2021 | |
31 August 2021 | Electronic delivery of CHESS holding statements and notifications: technical and process factsheet | |
31 August 2021 | ASX CHESS Replacement Documentation Release - August 2021 Release notes | |
31 August 2021 | Public Consultation on Tranche 3 and Combined Rules Package | Consultation paper |
6 August 2021 | Implementation & Transition Working Group Q&A – 28 July 2021 |
|
30 July 2021 | ASX CHESS Replacement Documentation Release - July 2021 Release notes | Release notes |
12 July 2021 | ASX CHESS Replacement Project Newsletter - July 2021 | |
9 July 2021 | Implementation & Transition Working Group Q&A - 30 June 2021 | Q&A - 30 June 2021 |
30 June 2021 | CHESS Replacement: Confirmed changes to netting and settlement workflow - Response to consultation feedback | Response |
30 June 2021 | ASX CHESS Replacement Documentation Release - June 2021 Release notes | Release notes |
30 June 2021 | Industry Test Strategy Information paper | Information paper |
11-Jun-2021 | ASX CHESS Replacement Project Newsletter - June 2021 | Newsletter - June 2021 |
10-Jun-2021 | Implementation & Transition Working Group Q&A - 3 June 2021 | Q&A - 3 June 2021 |
31 May 2021 | ASX Chess Replacement Documentation Release - May 2021 | Release notes |
30-Apr-2021 | ASX CHESS Replacement Documentation Release - April 2021 | Release notes |
23-Apr-2021 | ASX CHESS Replacement Project newsletter - April 2021 | Newsletter - April 2021 |
16-Apr-2021 | Technical Documentation - CDE 9.5 (mFund) code drop | Release notes |
9-Apr-2021 | Implementation & Transition Working Group Q&A - 31 March 2021 | Q&A – 31 March 2021 |
7-Apr-2021 | CHESS Replacement Issuer Readiness – Information Sheet | Information sheet |
1-Apr-2021 | ASX CHESS Replacement Documentation Release - March 2021 | Release notes |
1-Mar-2021 | Implementation & Transition Working Group Q&A – 23 February 2021 | Q&A – 23 February 2021 |
1-Mar-2021 | ASX CHESS Replacement CDE Uplift Release – February 2021 | Release notes |
25-Feb-2021 | ASX CHESS Replacement Project Newsletter – February 2021 | Newsletter – February 2021 |
18-Feb-2021 | ASX Consultation Paper on CHESS Replacement: Proposed changes to netting and settlement workflow. | Consultation Paper |
29-Jan-2021 | ASX CHESS Replacement Documentation Release - January 2021 | Release notes |
23-Dec-2020 | Implementation & Transition Working Group Q&A – 16 December 2020 | Q&A – 16 December 2020 |
18-Dec-2020 | ASX CHESS Replacement Project Newsletter – December 2020 | Newsletter – December 2020 |
17-Dec-2020 | ASX CHESS Replacement Documentation Release – December 2020 | Release notes |
16-Dec-2020 | ASX CHESS Replacement fact sheet for Payment Providers | Fact sheet |
4-Dec-2020 | ASX Data Governance under CHESS & CHESS Replacement | Information Paper |
30-Nov-2020 | Technical Documentation - CDE 9 code drop | Release notes |
5-Nov-2020 | ASX CHESS Replacement Project Newsletter - November 2020 | Newsletter - November 2020 |
30-Oct-2020 | ASX CHESS Replacement Documentation Release - October 2020 | Release Notes |
28-Oct-2020 | ASX response to consultation feedback: CHESS Replacement Confirmed Implementation Timetable | Response |
28-Oct-2020 | Media release - ASX announces new scope and go-live date for CHESS Replacement | Media Release |
27-Oct-2020 | Implementation & Transition Working Group Q&A – 7 October 2020 | Q&A – 7 October 2020 |
30-Sept-2020 | ASX CHESS Replacement Documentation Release - September 2020 | Release Notes |
25-Sept-2020 | ASX CHESS Replacement Project Newsletter - September 2020 | Newsletter - September 2020 |
24-Sept-2020 | Response to consultation feedback received on tranche 2 draft rule amendments | Response |
14-Sept-2020 | Technical Documentation - CDE 8 code drop | Release notes |
4-Sept-2020 | Implementation & Transition Working Group Q&A – 26 August 2020 | Q&A – 26 August 2020 |
31-Aug-2020 | ASX CHESS Replacement Documentation Release - August 2020 | Release Notes |
25-Aug-2020 | ASX CHESS Replacement Project Newsletter - August 2020 | Newsletter - August 2020 |
7-Aug-2020 | Implementation & Transition Working Group Q&A – 29 July 2020 | Q&A – 29 July 2020 |
5-Aug-2020 | Media release - CHESS Replacement replan consultation early observations | Media release |
31-July-2020 | ASX CHESS Replacement Documentation Release - July 2020 | Release Notes |
28-July-2020 | ASX CHESS Replacement Project Newsletter - July 2020 | Newsletter - July 2020 |
27-July-2020 | ASX CHESS Replacement fact sheet for participants | Fact sheet |
30-June-2020 | ASX Consultation Paper on CHESS Replacement Revised Implentation Timetable | Consultation paper |
23-June-2020 | ASX CHESS Replacement fact sheet for Issuers | Fact sheet |
29-May-2020 |
Technical Documentation - CDE 7 code drop |
|
22-May-2020 |
Response to consultation feedback received on Tranche 1 draft rule amendments |
|
22-May-2020 |
ASX CHESS Replacement Project Newsletter - May 2020 |
|
30-Apr-2020 | Technical Documentation - Release 8 (part II) | Release Notes |
24-Apr-2020 | ASX CHESS Replacement Project Newsletter - April 2020 | Newsletter - April 2020 |
2-Apr-2020 | Technical Documentation - Release 8 (part I) | Release Notes |
27-Mar-2020 | ASX CHESS Replacement Project Newsletter - March 2020 | Newsletter - March 2020 |
25-Mar-2020 | ASX to consult on CHESS replacement implementation timetable | Media Release |
3-Mar-2020 | Technical Documentation - CDE 6 code drop | Release Notes |
28-Feb-2020 | Technical Documentation - Release 7 (part II) | Release Notes |
25-Feb-2020 | ASX CHESS Replacement Project Newsletter - February 2020 | Newsletter - February 2020 |
31-Jan-2020 | Technical Documentation - Release 7 (part I) | Release Notes |
28-Jan-2020 | ASX CHESS Replacement Project Newsletter - January 2020 | Newsletter- January 2020 |
19-Dec-2019 | ASX CHESS Replacement Project Newsletter - December 2019 | Newsletter - December 2019 |
13-Dec-2020 | Technical Documentation - CDE 5 code drop | Release Notes |
29-Nov-2019 | Technical Documentation - Release 6 | Release Notes |
22-Nov-2020 | ASX CHESS Replacement Project Newsletter - November 2019 | Newsletter - November 2019 |
7-Nov-2019 | ASX National Issuer Roadshow Oct/Nov 2019 - CHESS Replacement update | Presentation slides |
5-Nov-2019 | Technical Documentation - CDE 4 code drop | Release Notes |
5-Nov-2019 | Technical Documentation - Release 5 (part II) | Release Notes |
23-Oct-2019 | ASX CHESS Replacement Project Newsletter - October 2019 | Newsletter - October 2019 |
27-Sep-2019 | Technical Documentation - Release 5 (part I) | Release Notes |
20-Sep-2019 | ASX CHESS Replacement Project Newsletter - September 2019 | Newsletter- September 2019 |
3-Sep-2019 | ASX CHESS Replacement System Access Pricing | Pricing Letter - September 2019 |
30-Aug-2019 | Technical Documentation - CDE 3 code drop | Release Notes |
26-Aug-2019 | ASX CHESS Replacement Project Newsletter - August 2019 | Newsletter - August 2019 |
26-Aug-2019 | ASX Media Release - ASX, Digital Asset & VMWare join forces on DLT | Media Release |
31-July-2019 | Technical Documentation - Release 4 | Release Notes |
19-July-2019 | ASX CHESS Replacement Project Newsletter - July 2019 | Newsletter - July 2019 |
17-July-2019 | Toronto Centre Podcast: Introducing the Newest Technology to Capital Markets: The Industry's Perspective - July 31, 2019 | Podcast - July 2019 |
5-July-2019 | Technical Documentation - What's New update | What's New |
28-June-2019 | Technical Documentation - CDE 2 code drop | Release Notes |
28-June-2019 | Technical Documentation - Release 3 (part II) | Release Notes |
20-Jun-2019 | ASX CHESS Replacement Project Newsletter - June 2019 | Newsletter - June 2019 |
30-May-2019 | Technical Documentation - Release 3 (part I) | Release Notes |
7-May-2019 | ASX Media Release – Successful opening of CDE for DLT testing | Media Release |
30-Apr-2019 | Technical Documentation update – Direct Connectivity & Testing | What’s New |
30-Apr-2019 | Technical Documentation – CDE 1 code drop | Release Notes |
4-Apr-2019 | Digital Asset Media Release – DAML Open Source | Media Release |
29-Mar-2019 | Technical Documentation – Release 2 | |
13-Mar-2019 | Technical Documentation update – Connectivity, Environments & Testing | What’s New |
12-Mar-2019 | ASX details on the costs to access the CHESS Replacement system for clearing and settlement participants | ASX letter |
20-Dec-2018 | Technical Documentation update – Revisions | What’s New |
14-Dec-2018 | Technical Documentation – Release 1 | Release Notes |
12-Dec-2018 | Overview of Technical Documentation | |
3-Oct-2018 | Overview on connectivity options |